In January 2026, Collier County's coastal staff told an advisory committee that Wiggins Pass, the inlet at the top of Vanderbilt Beach, had filled in so much that people were having a hard time getting in and out at low tide. The dredge they asked for that month is the one working the inlet now, around the clock, until about the end of November.
You may have seen the barge, the pipeline or the closed parking lot at Delnor-Wiggins Pass State Park this fall. They are part of something the county does on a schedule, which happens to be running late this year. Wiggins Pass fills back in no matter how often it is cleared. The county keeps a written plan for where the sand goes and a calendar for when the next round is due. The 2026 dredge was due anyway, and the hurricanes filled the pass badly while the county waited on a federal permit. Then the start date moved from spring to late September.
The Pass Was Supposed to Be Done by May
The record starts at the Coastal Advisory Committee's January 8, 2026 meeting, published in the committee's June 11, 2026 agenda packet. Andrew Miller of Collier County's coastal zone staff told the committee the county had wanted to dredge Wiggins Pass "for the past couple years," pending an Army Corps of Engineers permit. The minutes summarize his reasoning this way:
"with recent hurricanes, it's filled in significantly, to the point where people are having hard time to get in and out at low tide."
The permit had arrived a few weeks earlier. Bids were due January 19. The committee approved a project "scheduled for March/April 2026," with Tourist Development Tax spending capped at $2 million. Asked how long the work would take, Miller said he hoped for six weeks to two months at most. The deadline was firm: sea turtle nesting season starts May 1, and the work had to be finished before then.
That same January meeting explains why Doctors Pass is now part of the story. In the 2021 to 2022 cycle, the county bid both inlets under one contract so a single dredge crew could do both. This time, with the Wiggins permit's timing unknown, staff split them into two separate projects so one wouldn't hold up the other. The minutes say Doctors Pass "needs it as bad as Wiggins does."
The spring window passed without a dredge. Here is how the schedule moved:
| When it was said | Where | Planned start for Wiggins Pass |
|---|---|---|
| January 8, 2026 | Coastal Advisory Committee | March/April 2026, done before May 1 |
| June 11, 2026 | Coastal Advisory Committee | July, with Doctors Pass in August |
| October 16, 2026 | U.S. Coast Guard notice to mariners | Dredging from about September 28, estimated done November 30 |
The two inlets ended up together after all, under one combined Wiggins Pass and Doctors Pass maintenance dredging contract. The county's bid results list Sea Hawk Maritime, LLC as the lowest of four bidders at $2,074,750. The Board of County Commissioners agenda recommended awarding the contract to Sea Hawk at that figure. In January, $2 million was the conservative estimate for Wiggins Pass alone. The bid that came in covers both inlets for about the same amount.
What's on the Water Until Late November
For anyone whose boat goes out through Wiggins Pass, the late start matters more than anything else in this story. The dredge is working in season, while boat traffic is picking back up. The Coast Guard's Local Notice to Mariners, dated October 16, 2026, says Sea Hawk Maritime began mobilizing on or about September 23 and started dredging on or about September 28. It also says this about the operation:
- Work runs 24 hours a day, seven days a week.
- The vessel Dredge Clearwater monitors VHF-FM channels 13 and 16.
- Floating and submerged pipeline, both plastic and steel, carries the dredged material, along with work vessels, a dredge barge, booster pump barges, crane barges, tugs and buoys.
- The equipment is lit and marked under Coast Guard rules, but its layout "can change daily," and vessels may be working in more than one spot at once.
- Mariners are urged to use extreme caution, run at their slowest safe speed to keep wake down, and pass only after passing arrangements have been made.
The estimated finish is November 30, 2026. Treat that as the Coast Guard's estimate, not a guaranteed date. This year's schedule has already moved twice. The notice covers the combined two-inlet project and doesn't give a separate start date for Doctors Pass. If the January plan holds, the crew will work through Wiggins Pass first and then move south.
What's Different at Delnor-Wiggins
On the beach side of the inlet, the dredge is the newest of several changes at Delnor-Wiggins Pass State Park this fall, and each one changes how a visit works.
The park's alert, effective September 25, 2026, says equipment will operate on and near the beach during the project and parking lot four will close from time to time. Three days later, on September 28, the park changed how visitors pay. Entrance fees are now paid at card-only touchscreen kiosks around the park and at the boat ramp, and the printed receipt goes on your dashboard. The fee is $6 per vehicle, and the park is open 8 a.m. to sunset every day of the year.
One older alert is still posted. Since April 18, 2025, the park has had no drinking water and has used temporary restrooms. Its amenities page lists portable restrooms at the parking areas and free beach wheelchairs available first come, first served. A Florida State Parks FAQ puts the timeline for fully replacing the bathrooms at "2 years +," but the document is undated and gives no start date. Bring water.
When lot four is closed, the county beaches to the south are the nearby alternatives, and their parking works differently. Collier County residents can get a free beach parking permit with proof of residency. The county's beach parking page lists the documents you need and where the sticker goes on the windshield. Visitors without a permit pay a flat $10 a day at Vanderbilt Beach Park and Conner Park, according to the county's mobile pay sheet. If guests are coming for Thanksgiving, that is the rate to tell them about. The state park's $6 fee is separate and applies to everyone, permit or not.
Where the Sand Is Supposed to Go
Dredging the pass isn't only about removing sand. It also returns sand to the beaches that lost it. Wiggins Pass has an inlet management plan that sends one-third of dredged sand north and two-thirds south. Miller told the committee in January that a single dredge doesn't have to follow that split. Engineers survey the beaches on each side each time and decide, so the one-third, two-thirds balance works out across many years.
For 2026, the January plan sent the sand to Delnor-Wiggins, between FDEP survey monuments R-18 and R-20, south of the inlet. The plan estimated about 75,000 cubic yards from Wiggins Pass. In June, preliminary bids for both inlets together came to about 122,000 cubic yards at roughly $18 per cubic yard. Those are the planned placement and estimated volumes. The final volumes will be known once the work is done.
A Pass That Keeps Filling In
This is why the work comes back every few years. As Collier County Coastal Zone Management explained to Spotlight News before the last full dredge in 2022, sand moving along the coast turns into the inlet, which shallows the channel and takes sand away from the beaches north and south of it. Before that dredge, the channel had been as shallow as 3 feet, and 2 feet in some spots.
The county's funding application, included in the September 10, 2026 Coastal Advisory Committee packet, lists how much has been removed from the pass over the past 15 years:
| Year | Cubic yards removed from Wiggins Pass |
|---|---|
| 2011 | 49,900 |
| 2013 | 107,370 |
| 2015 | 9,400 |
| 2018 | 96,000 |
| 2020 | 48,041 |
| 2022 | 66,033 |
Six removals in 11 years. Some were full maintenance projects and some were smaller interim cleanups. The 2022 dredge, which ran from January 26 to March 10, 2022, was an emergency project, needed because storms after a small interim dredge in March 2020 left shoals that blocked navigation. In January, Miller called the 2026 project "right on four- to five-year cycle." He said the county would have liked to dredge a year earlier but couldn't because of the storms.
The same application says what comes next. The county describes 2026 as a complete maintenance dredge of the channel and expects an interim channel dredge in 2028/2029. It also says FDEP staff found the project eligible for a 50% state cost share. So the channel boaters get back in December is expected to start filling in again, and an interim dredge is already on the calendar about two to three years out, sooner if storms speed things up the way they did after 2020.
If your plans this season involve a boat lift on Vanderbilt Lagoon, a Gulf-access canal home, or the timing of a sale around how easy it is to reach the Gulf, I'm glad to talk through what this dredge cycle means for the waterfront streets near the pass. Susan Barreiro is just a call or note away. Let's Connect.